In Saudi Arabia the Saudi Building Code sets the design rules and a handful of authorities approve the result. Here is who governs what, and what it does to your quantities.

Saudi projects are designed to the Saudi Building Code (SBC) — SBC 801 for fire, SBC 401 for electrical, SBC 501 for mechanical, SBC 601 for energy and SBC 701 for plumbing — and approved by the authority that owns each system. Fire systems go through the General Directorate of Civil Defense on the Salamah platform; power goes to the Saudi Electricity Company; water and drainage to the National Water Company.

Who governs what

SystemAuthorityApproval / standard
Fire alarmGeneral Directorate of Civil Defense (GDCD)Design approval and installation permit via Salamah (998); SBC 801
Sprinklers, hydrants and fire pumpsGeneral Directorate of Civil Defense (GDCD)Design approval and installation permit via Salamah; SBC 801
Power distribution, DB panels, earthingSaudi Electricity Company (SEC)SEC electrical design approval and connection permit; SBC 401
Lightning protectionCivil Defense, within the fire and electrical submittalReviewed within the SBC 401 / SBC 801 approval
HVAC and ventilationMunicipality (Amanah, MOMRAH) with Civil Defense for smoke controlBuilding permit compliance; SBC 501 and SBC 601
Water supply and drainageNational Water Company (NWC)NWC connection approval / NOC; SBC 701
CCTVMinistry of InteriorPrior approval under the Law of the Use of Security Surveillance Cameras
Structured cabling and Wi-FiCommunications, Space & Technology Commission (CST)CST type approval for equipment; TIA-568 / ISO/IEC 11801 for cabling
Access controlNo statutory approvalEgress interlocks verified under the Civil Defense SBC 801 approval

What this actually does to your BOQ

Fire is one submission, so price it as one package

Fire alarm, sprinklers, hydrants, fire pumps and smoke control all go to Civil Defense together. A change in one — a larger pump, a revised zone — reopens the submission. Keep these systems consistent in the BOQ and price the approval effort once, not per system.

Testing and certification are line items

These belong in the BOQ as priced items, not absorbed into preliminaries.

CCTV needs approval before it is installed

Under the surveillance cameras law, camera locations, coverage and recording are approved before installation. Leave room in the programme, and in the BOQ, for the design submission and any changes it asks for.

Requirements change. The table above reflects the position as generally applied, but codes, approval routes and approved lists are updated, and local practice varies. Confirm current requirements with the relevant authority or your compliance consultant for any project you are pricing — this guide is a starting map, not a substitute for that check.

Building compliance into the BOQ rather than bolting it on

The practical habit worth adopting is to record, against each system in your BOQ, the governing authority, the required approval and the required test. It takes a few minutes per system and it prevents the two expensive failures: pricing equipment that cannot be used, and omitting testing that must be done.

Quantora attaches these requirements to each system automatically, based on the project's country and city, so the compliance position sits next to the quantities rather than in a separate document nobody opens.