Singapore runs approvals through one channel: a Qualified Person submits through CORENET and each agency clears its own part. Here is who governs what, and what it does to your quantities.

In Singapore, building plans are submitted through CORENET by a Qualified Person (QP), and each agency clears its own part: the Singapore Civil Defence Force (SCDF) for fire safety under the Fire Code, the Energy Market Authority (EMA) through Licensed Electrical Workers for electrical installations, PUB for water and drainage, and IMDA for telecommunication facilities.

Who governs what

SystemAuthorityApproval / standard
Fire alarmSingapore Civil Defence Force (SCDF)Fire Safety Plan approval via CORENET; Fire Code 2023; SS 645
Sprinklers and fire pumpsSingapore Civil Defence Force (SCDF)Fire Safety Plan approval; SS CP 52
Hydrants and hose reelsSingapore Civil Defence Force (SCDF)Fire Safety Plan approval; SS 575
Power distribution, DB panels, earthingEnergy Market Authority (EMA); SP Group for supplyLicensed Electrical Worker sign-off; SS 638
Lightning protectionBuilding and Construction Authority (BCA), through the QPSS 555
Mechanical ventilation and smoke controlSCDF for smoke control; NEA for general ventilationFire Code Chapter 7; SS CP 13
Water supply and drainagePUB, Singapore's National Water AgencyWater supply application by a licensed plumber; sanitary plan approval
Structured cablingInfocomm Media Development Authority (IMDA)COPIF clearance in the CORENET submission
CCTVSingapore Police Force guidance; PDPC for dataNo approval; SPF video surveillance standard; PDPA

What this actually does to your BOQ

Telecom facilities are an approval, not an extra

IMDA's Code of Practice for Info-communication Facilities in Buildings (COPIF) sets the telecom rooms, risers and lead-in pipes the building must provide. Those are civil and containment quantities that belong in the BOQ from the start, not a late addition from the telecom contractor.

Testing and certification are line items

These belong in the BOQ as priced items, not absorbed into preliminaries.

Named professionals carry the sign-off

The QP, the Licensed Electrical Worker and the licensed plumber each sign for their part. Their fees and their availability affect the price and the programme.

Requirements change. The table above reflects the position as generally applied, but codes, approval routes and approved lists are updated, and local practice varies. Confirm current requirements with the relevant authority or your compliance consultant for any project you are pricing — this guide is a starting map, not a substitute for that check.

Building compliance into the BOQ rather than bolting it on

The practical habit worth adopting is to record, against each system in your BOQ, the governing authority, the required approval and the required test. It takes a few minutes per system and it prevents the two expensive failures: pricing equipment that cannot be used, and omitting testing that must be done.

Quantora attaches these requirements to each system automatically, based on the project's country and city, so the compliance position sits next to the quantities rather than in a separate document nobody opens.

Let Quantora do this from your drawings

Choose the project's country and city, upload a floor plan, and Quantora returns a complete bill of quantities in minutes — every item counted and located, with the governing authority, approval and test shown against each system.

Start free — no credit card →